The goals were achieved by designing an adaptive re-use of the existing building,
retaining the Granary’s form, structure and foundation, transforming
a drafty, dark industrial building into an efficient, bright structure
using Savings by Design and LEED criteria in addition to standard
design practices. The project received Designer and Owner incentives
from the Savings by Design program and is in the last phases of
completion of Leadership in Energy and Environmental Design (LEED,
a silver certification pending) certification.
The Renovation of the site included several small buildings that have been re-worked
into an Art Gallery space and a trash/recycling enclosure. The
corn sifting building was lifted from its foundation and relocated
to provide storage, a recycling center and a trash enclosure. The
relocation was accomplished by lifting the entire structure over
the remaining 50’ main silos, with a crane. The parking lot was
constructed of permeable concrete, which reduces run-off and re-charges
the aquifers.
The existing concrete ramp that served the main entry was reconstructed for
access compliance and outdoor seating. The elevated foundation
would have necessitated a very long ramp to meet ADA requirements.
Instead, a three stage elevator with exterior access was installed
next to the building including a stair core. This allowed us to
construct outside the existing structure without impacting the
existing structure or foundation. The original truck scale remained
in place and is part of the path leading to the main entry. At
the front side of the entry is a small storage building and mail
box area, replacing the original main scale building.
The existing building structure was inspected by a structural engineer, due
to the change in occupancy and to verify if it met current standards.
The results indicated it would be acceptable if no additional loads
were placed upon it. The new interior, two and three story structure,
was constructed within the existing exterior metal structure, erecting
a building wit in a building. This allowed us to keep the original
structure and highlight it by sandblasting the original structure
to clean it and then insulating on top of the existing roof, retaining
the original metal roofing and siding.
Go to top
The building’s interior openness allowed for creative solutions including a mezzanine
overlooking the first floor with an accessible steel catwalk and
a third floor space that can be developed in the future. The structure
allowed windows to be located in such a way as to emphasize views
while retaining the nature of the building. The open ceilings created
an opportunity to provide a unique and flexible approach to heating
and air conditioning by the use of duct sox. The original floor
plan, of 6,000 square feet on one level, was expanded vertically
to provide over 13,000 square feet, with an additional 1,200 feet
added for restroom and elevator and stair cores. Restrooms use
low water-use fixtures and waterless urinals.
The adaptive reuse of existing structure and the understanding of what elements
from a construction standpoint made sense to maintain and to construct
new allowed the construction process to proceed in a clear and
organized fashion. There were a number of obstacles to development;
demolition and cleanup of the site that had been abandoned for
over seven years resulted in significant cost. The summer of 2004
escalation of steel prices also adversely affected construction
cost. Recycling concrete by using it to fill in open underground
pits, once used for grain storage, saved the cost and disposal
of hauling tons of concrete. The project recycled almost 90% of
all materials and 100% of the existing steel tanks and structures.
Preservation/Restoration
Acknowledgement and incorporation of the historic Granary elements into the
building, with the goal of sustainability, the project focuses
not just on the historic nature but takes the essence of the Granary
and follows that vocabulary throughout the project. During and
after the construction people from many walks of life have come
to remember what it was like when it was a functional feed granary
running 24/7 and others interested in what the past held.
Preservation of the past was very important in developing the project. Architectural
elements were retained including the original silos as well as
the superstructure that originally fed the silos. The Granary had
a star on the highest structure and that too was reconstructed
and installed, reminding the community of the past.
Go to top
Many elements were maintained or re-used; augers for lifting feed became elements
that help bounce light off of the ceiling, the original scale was
re-worked and re-located to outside the new restrooms and provides
a fun place for adults and children to experience the past. Photos
and maps of the Granary when it was in it’s heyday and when it
was abandoned line the hallway and provide for an interpretive
historic look into a the not-so-long ago history of this once agricultural
town now part of bustling Silicon Valley.
Environmental Advancement
Materials and methods were key to the adaptive re-use and environmental advancement.
Following the LEED criteria and working with Savings By Design
was a natural extension of re-using the existing building and the
goal of designing a sustainable building. Re-use of the metal structure,
roofing and some siding was important as well as re-cladding with
Galvalume contributing to the percent recycled content of the project.
The Galvalume also provided a finished surface reducing material
use. The original steel frame and the roofing were sandblasted
to provide a clean interior ceiling and structure. To maintain
the look of the original Granary while providing greater comfort
and energy efficiency, a new metal ‘cool’ roof was installed on
the top of the old roof and 95% recycled content insulation was
blown in allowing for complete fill and a minimum of R30.
The project embodies sustainable design concepts including natural lighting
and ventilation through the use of low E double-pane operable windows,
extra insulation –blown in 95% recycled , recycled products, renewable
resources, low or zero VOC paints, glues and sealant materials,
a building recycling center, low water restroom fixtures, low energy
use and re-use of the existing interesting structure and floors.
This well insulated building stays warm in the winter and cool
in the summer. On a summer morning windows are opened early so
that the prevailing breeze flows through cooling the building and
reducing the need for air-conditioning. Building performance is
26.6% better than California Title 24 standards. This was achieved
by the increased insulation, window protection and high efficiency
HVAC units.
Materials used in the design include some unique approaches, a “storefront”
constructed of wheat board and Trex ( a product with high recycled
content and the decking material used in the exterior decks as
well) and a theme using wheat board for edging and capping. Cork
flooring was used on the second floor mezzanine and Green Guard
carpet squares were used in some of the office areas where the
original concrete flooring was not used. All other floors were
the original concrete, stained and sealed with a zero VOC stain
and finish. All casework is wheat board sealed and finished.
Window coverings and a translucent overhang helps to monitor heat gain in the
summer and allow for interior day-lighting. All interior lighting
remains with in the building decreasing light pollution. The Kalwall
skylights give a consistent interior glow, decreasing the need
for lighting. All interior rooms have windows that allow for views
and natural lighting from the outside. Al principally habitable
spaces are adjacent to operable windows.
The building inhabitants enjoy the adjacent trains passing within 10 feet of
exterior office windows (well insulated so virtually no sound),
the natural light, the original use of every-day-materials, the
sustainability and low energy costs and the uniqueness of this
historic and sustainable building.
Go to top |